If the first month of our custom home build felt like a whirlwind of excitement watching our empty lot transform into a foundation, month two brought an entirely different kind of thrill. This is the stage where a house actually starts to look like, well, a house. Walls went up, a roof appeared overhead, and suddenly we were walking through rooms that just weeks earlier existed only on paper.
We wanted to share a detailed, honest look at everything that happened during the second month of our build, including the framing progress, roofing installation, and the rough in work for plumbing, HVAC, and electrical systems. If you are currently in the middle of your own custom home build, or just beginning to plan one, we hope walking through our exact experience helps you know what to expect during this genuinely exciting phase. Let us walk you through it month by month. ๐งฑโจ
Picking Up Where We Left Off ๐
At the end of our first month, our builder had completed the first floor framing, including the ceilings for that level. For reference, we had opted for ten foot ceilings on our first floor, a decision that was already starting to make the space feel noticeably more open and grand even in its unfinished state.
๐ Our first floor layout includes the living room, kitchen, pantry, powder room, dining nook, formal dining room, my office, and a mudroom ๐ค๏ธ We had been fortunate with weather throughout the first month, experiencing very little rain that could have slowed progress ๐ Framing had moved along far faster than we originally anticipated, setting an encouraging tone heading into month two
With that strong start behind us, we were excited to see how quickly the second month would bring our home closer to a fully enclosed structure.
Second Floor Framing Takes Shape ๐ช
Early in month two, the framing crew shifted their focus upward, moving from our completed first floor to the second story of our home.
๐งฑ Watching the second floor walls go up gave us our first real sense of the home’s overall height and scale ๐ช Window openings for the second floor started taking shape, and we could finally picture natural light flowing through spaces we had only seen on our floor plan before ๐๏ธ The framing crew worked efficiently, and within a relatively short window, the second floor walls and ceiling structure were substantially complete
Seeing the full two story frame standing on our lot for the first time was genuinely one of the most exciting moments of the entire build process so far. It was the point where the project stopped feeling abstract and started feeling like our actual future home.
Roof Trusses and Roofing Installation ๐
Once the framing reached a sufficient stage of completion, our builder moved forward with installing the roof trusses, quickly followed by the actual roofing materials.
๐บ Roof trusses were delivered and set in place over just a few work days, giving the home its final overall silhouette ๐ง๏ธ Getting the roof on as quickly as possible mattered significantly, since it protects the framing lumber and interior spaces from potential weather damage moving forward ๐๏ธ Once trusses were set, the roofing crew moved in to install decking and the final roofing material, officially enclosing the top of our home
This milestone genuinely changed the entire feel of visiting the construction site. Walking through rooms that were now fully covered overhead, rather than open to the sky, made the whole experience feel significantly more real.
Comparison Table: Month 2 Construction Milestones ๐งพ
| Stage | What Happened | Approximate Timing Within Month 2 |
|---|---|---|
| Second Floor Framing | Walls and ceiling structure completed | Early month |
| Roof Trusses | Delivered and set in place | Early to mid month |
| Roofing Installation | Decking and roofing material installed | Mid month |
| HVAC Rough In | Ductwork installed throughout walls and ceilings | Mid to late month |
| Plumbing Rough In | Supply, waste, and vent lines installed | Late month |
| Electrical Rough In | Wiring, boxes, and panel connections installed | Late month |
Understanding the Rough In Phase ๐ง
Once our home was fully framed and enclosed with a roof, the project shifted into what is commonly referred to as the rough in phase. This is the stage where the essential mechanical systems, including HVAC, plumbing, and electrical, are installed inside the walls, floors, and ceilings before insulation and drywall close everything up.
๐ This phase typically follows a specific trade sequence to avoid conflicts between the different systems being installed ๐ฌ๏ธ HVAC generally goes in first, since ductwork requires significant space and the most rigid routing requirements ๐ฐ Plumbing typically follows next, since drain lines have strict slope requirements that limit their routing flexibility โก Electrical wiring usually comes last among these three trades, since electricians can more easily route around the space already claimed by the larger HVAC and plumbing systems
Understanding this sequence helped us make sense of why certain trades appeared on our job site before others throughout this stage of the build.
Watching the HVAC System Come Together ๐ฌ๏ธ
Our HVAC contractor was among the first specialty trades to begin work once our home was fully enclosed.
๐ง Ductwork began threading through our ceiling joists and interior walls, following the specific routing our HVAC design called for ๐ Seeing the physical ductwork in place helped us better understand how conditioned air would eventually flow throughout each room of our home ๐ We also finalized a few remaining decisions during this stage, including vent placement in certain rooms where our original plans needed slight adjustments based on real world framing conditions
This stage reinforced just how much behind the scenes planning goes into a system that most homeowners never think twice about once their home is finished and comfortable.
Plumbing Rough In Progress ๐ฟ
Following HVAC, our plumbing contractors moved through the home installing supply lines, drain lines, and vent piping throughout the walls and floors.
๐ฐ Rough in plumbing was installed for every bathroom, our kitchen, the laundry room, and additional fixtures throughout the home ๐ Bathtub and shower pan rough ins were set during this stage, locking in the exact placement for these fixtures ahead of final installation later in the build ๐ฅ Our gas line stub outs, including the connection point for our range, were also finalized during this phase
Watching the plumbing rough in come together gave us a much clearer picture of exactly how water would move throughout our home, and it made us appreciate just how much precise planning goes into something we will ultimately never see once walls are closed up.
Electrical Rough In and Panel Installation โก
Rounding out the major rough in trades, our electrical contractors began wiring the home, setting outlet and switch boxes, and running the necessary home run feeds back to our main electrical panel.
๐ก Outlet and switch locations throughout the home were installed according to our finalized electrical plan from earlier selection meetings ๐ This stage represented our last real opportunity to make any final adjustments to outlet placement before walls would eventually be closed up ๐ Our main electrical panel was set and connected, preparing the home for the eventual utility connection
This was another important reminder throughout the process that once drywall goes up, adjusting these behind the wall systems becomes significantly more difficult and costly, reinforcing just how important those earlier planning meetings truly were.
Inspections Along the Way ๐
Throughout this phase of rough in work, our project also underwent several required inspections before construction could move forward to the next stage.
โ Inspectors reviewed the HVAC, plumbing, and electrical rough in work to confirm everything met local building code requirements ๐ These inspections needed to be passed before our builder could move forward with insulation and drywall installation ๐ฐ๏ธ While these inspection points did add some natural pauses to the visible progress, they provided genuine peace of mind knowing our home’s essential systems were being properly verified
Understanding that these inspection points were a normal, expected part of the process helped us stay patient during the moments when visible progress on site slowed down slightly.
Comparison Table: Trade Sequence During Rough In ๐งพ
| Trade | Typical Order | Why This Sequence Matters |
|---|---|---|
| HVAC | First | Requires the most rigid ductwork routing and space |
| Plumbing | Second | Drain lines have strict slope requirements limiting flexibility |
| Electrical | Third | Wiring can more easily route around already installed systems |
| Inspections | Throughout | Confirms code compliance before walls are closed |
Our Overall Impressions of Month Two ๐ญ
Looking back at this stage of our build, a few genuine takeaways stood out to us that we think other homeowners going through their own custom build should know.
๐ The pace of visible progress during framing and roofing felt incredibly fast and exciting ๐ง Once rough in work began, progress became noticeably less visually dramatic, even though the work happening behind the scenes was just as important ๐ Staying in regular communication with our builder throughout this stage helped us understand what was happening even when visits to the job site did not show major visible changes week to week ๐ง We found it genuinely helpful to educate ourselves on the typical rough in trade sequence, since it helped set realistic expectations for what we would see during each site visit
This shift in pacing, from the fast and visually dramatic framing stage to the slower, more detail oriented rough in phase, is something we wish we had better understood going into this month, since it would have helped manage our expectations even further.
Tips for Homeowners Currently in This Build Stage ๐ฏ
Based on our own experience during month two of our build, here are a few pieces of advice we would offer to other homeowners currently navigating this same stage.
๐ Stay closely involved during electrical rough in, since this is genuinely your last practical opportunity to adjust outlet and switch placement ๐ธ Take plenty of photos throughout the rough in phase, since these images can be genuinely valuable reference points for future renovations or repairs ๐๏ธ Expect the pace of visible progress to slow down somewhat once rough in work begins, and know that this is a completely normal part of the process โ Ask your builder about upcoming inspection points so you understand what needs to happen before the project can move forward to insulation and drywall
Frequently Asked Questions โ
How long does the rough in phase typically take during a custom home build? This varies depending on the size and complexity of the home, but rough in work for HVAC, plumbing, and electrical combined often takes several weeks to complete, particularly once inspection scheduling is factored in.
Why does HVAC typically get installed before plumbing and electrical? HVAC ductwork requires the most rigid routing and the greatest amount of physical space, so installing it first allows plumbing and electrical trades to route their own systems around the ductwork more easily.
Is it normal for visible progress to slow down after framing is complete? Yes, this is a very normal part of the custom home building process. Framing and roofing tend to show dramatic, fast visible progress, while rough in work, though equally important, happens largely behind the walls and is less visually obvious.
What should homeowners pay closest attention to during electrical rough in? This is typically your last opportunity to easily adjust outlet, switch, and fixture wiring locations before walls are closed up, so it is worth reviewing this stage carefully with your builder.
Do all custom home builds require inspections during the rough in phase? Yes, inspections for HVAC, plumbing, and electrical rough in work are a standard requirement before a project can move forward to insulation and drywall in most jurisdictions.
Final Thoughts ๐ญ
Month two of our custom home build brought some of the most visually exciting progress we have experienced so far, from watching our second floor framing rise into place to seeing our roof finally installed overhead. The shift into rough in work for HVAC, plumbing, and electrical reminded us just how much essential, behind the scenes effort goes into building a home that functions smoothly for years to come.
If you are currently navigating this same stage of your own custom home build, we hope our experience helps set realistic expectations for what to watch for and what questions to ask along the way. Stay tuned as we continue sharing our journey through the next stages of construction, including insulation, drywall, and the exciting interior finishes still ahead! ๐ก๐จ